Mast Road

Location of roadwork:
Joy Road to Strawberry Lake Road

Township:
Webster

When is the work being done:
08/19

Description of work:
Chipseal

Impact on Traffic:
Daytime Road Closure

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

July 29, 2019 Daytime Road Closure: Mast, Strawberry Lake, N. Territorial (Webster Twp)

WHEN: Tuesday, July 30, 2019

WHERE: The following roads in Webster Township:

  • North Territorial Road between Webster Church Road and Maple Road
  • Mast Road between North Territorial Road and Strawberry Lake Road
  • Strawberry Lake Road between Mast Road and the county line

WHY: Preventative maintenance – chip seal

BACKGROUND: On Tuesday, July 30, 2019, the Washtenaw County Road Commission (WCRC) will close the following roads in Webster Township for preventative maintenance:

  • North Territorial Road between Webster Church Road and Maple Road
  • Mast Road between North Territorial Road and Strawberry Lake Road
  • Strawberry Lake Road between Mast Road and the county line

The road improvements are expected to take approximately one day. However, all dates are tentative and subject to change due to weather conditions. Once the roads are back open, drivers are advised to lower their speeds to 35 mph while the stone settles.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org

For more information about WCRC road closures visit wcroads.org/news-resources/road-work-advisories/.

ISSUE DATE: 07/29/19

July 25, 2019 Daytime Road Closure: Mast Road & Strawberry Lake Road (Webster Twp)

WHEN: Monday, July 29, 2019

WHERE: Mast Road between N. Territorial Road and Strawberry Lake Road AND Strawberry Lake Road between Mast Road and the county line in Webster Township

WHY: Preventative maintenance – chip seal

BACKGROUND: On Monday, July 29, 2019, the Washtenaw County Road Commission (WCRC) will close both Mast Road between N. Territorial Road and Strawberry Lake Road AND Strawberry Lake Road between Mast Road and the county line in Webster Township for preventative maintenance.

The road improvements are expected to take approximately one day. However, all dates are tentative and subject to change due to weather conditions.

Once the road is back open, drivers are advised to lower their speeds to 35 mph while the stone settles.

CONTACT: If you have any questions concerning this work, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org

For more information about WCRC road closures visit wcroads.org/news-resources/road-work-advisories/.

ISSUE DATE: 07/25/19

Contact information:
Ken Harris or Adam Lape
    • (734) 327-6696 or (734) 327-6697