Maple Road

Location of roadwork:
Between Textile Road and Ann Arbor-Saline Road

Township:
Lodi, Pittsfield

When is the work being done:
August 23 - Sept. 2

Description of work:
Mill & Resurfacing

Impact on Traffic:
Intermittent lane closures

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage

Latest Updates

August 19, 2021 Lane Restrictions: Maple Rd (Lodi, Pittsfield Twps)

WHEN: Starting on Monday, August 23, 2021

WHERE: Maple Rd between Textile Rd and Ann Arbor-Saline Rd in Lodi and Pittsfield Townships

WHY: Road resurfacing

BACKGROUND: Starting on Monday, August 23, 2021, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Maple Rd between Textile Rd and Ann Arbor-Saline Rd in Lodi and Pittsfield Townships.

The road will not be closed to traffic, but delays are likely due to lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvement is expected to take approximately 2 weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions, please contact Mike Bernbeck, project manager (734) 327-6654, or via email at bernbeckm@wcroads.org.

ISSUE DATE: 08/19/21

Contact information:
Mike Bernbeck
    • (734)-327-6654
Helpful Links