Location of roadwork:
Jackson Rd Bridge, over Mill Creek, between Steinbach Rd and Parker Rd
Township:
Lima
When is the work being done:
2023
Description of work:
Bridge Preservation, Preventative Maintenance
Impact on Traffic:
Intermittent lane closures
Funding Source(s):
Michigan Transportation Fund (MTF)
Latest Updates
Construction is complete on the Jackson Rd Bridge, over Mill Creek, between Steinbach Rd and Parker Rd in Lima Township.
On Friday, August 11, 2023, the contactor completed the epoxy overlay on the bridge deck surface. All restrictions have been lifted.
The contractor will return at a later date to place the pavement markings.
Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.
Pictured is the completed epoxy overlay on the Jackson Rd Bridge, over Mill Creek, between Steinbach Rd and Parker Rd in Lima Township.