Huron River Dr Bridge

Location of roadwork:
Huron River Dr Bridge, over Huron River, between Tubbs Rd and Wagner Rd

Township:
Scio

When is the work being done:
June 20023

Description of work:
Bridge Preservation, Preventative Maintenance

Impact on Traffic:
Road closure and lane restrictions

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

August 12, 2023 Project Update: Project Complete!

Construction is complete on the Huron River Dr bridge, over Huron River, between Tubbs Rd and Wagner Rd in Scio Township.

On Saturday, August 12, 2023, the contactor completed the epoxy overlay on the bridge deck surface. Motorists can expect the removal of the temporary traffic control next week.

The contractor will return at a later date to place the pavement markings.

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.

Huron River Drive Bridge over the Huron River between Tubbs and Wagner

Pictured is the epoxy overlay that was completed on the Huron River Dr bridge, over Huron River, between Tubbs Rd and Wagner Rd in Scio Township.

July 25, 2023 Project Update: Project Complete!

Construction on the Huron River Dr bridge, over Honey Creek, between Tubbs Rd and Wagner Rd in Scio Township, is complete!

On Saturday, the contactor completed the epoxy overlay on the bridge deck surface.  All restrictions have been lifted.

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.

Pictured is the epoxy overlay that was completed on the Huron River Dr bridge, over Honey Creek, between Tubbs Rd and Wagner Rd in Scio Township.
June 28, 2023 Project Update: Construction Is Progressing

Construction is progressing on the Huron River Dr bridge, over the Huron River, between Tubbs Rd and Wagner Rd in Scio Township.  

Repairs to the bridge deck and concrete barriers are continuing this week. The contractor removed and replaced the deck joint and poured concrete. While this portion of the deck is curing, work will continue on the south bridge barrier. We expect to pour the concrete for the south bridge barrier and reopen the road to two-way traffic by the end of this week.    

The last step for this bridge preventative maintenance work is an epoxy application to the bridge deck surface, which will be performed in approximately one month. The temporary signals will remain in flashing yellow until the contractor returns. We appreciate your patience while we complete these important bridge maintenance items to keep our bridges in good condition. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.  

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org 

Pictured is the concrete that was poured for the bridge deck join on Huron River Dr, over the Huron River, between Tubbs Rd and Wagner Rd in Scio Township.
June 15, 2023 Project Update: Construction Is Moving Along

Heads up Scio Township! Concrete repairs have been completed on the westbound lane of the Huron River Dr bridge, located over the Huron River, between Wagner Rd and Tubbs Rd.

Traffic has been moved to the westbound lane to begin repairs on the eastbound lane and south bridge barrier. This work is expected to take approximately one week to complete.

Once repairs have been completed throughout the project limits, the concrete will cure for a minimum of 28 days before crews return to complete the project. WCRC will continue to send out updates as the project progresses.

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647 or via email at murphyn@wcroads.org.

Pictured below is the repairs taking place on the Huron River Dr bridge, over the Huron River, between Tubbs Rd and Wagner Rd in Scio Township.
June 12, 2023 Project Update: Construction Is Going Well!

The preventative maintenance work on the Huron River Dr bridge, over the Huron River, between Wagner Rd and Tubbs Rd in Scio Township has been going well.

The contractor is continuing to make the necessary concrete repairs on the bridge railing and at the expansion joint. The concrete work on the north side of the bridge is expected to be completed by the end of this week under lane restrictions. Once completed, the contractor will move to the south half of the bridge to begin repairs.

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.

Have questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.

Pictured above are the concrete repairs that took place on the Huron River Dr bridge, over the Huron River, between Wagner Rd and Tubbs Rd in Scio Township.
May 25, 2023 Lane Restrictions: Huron River Dr Bridge (Scio Twp)

WHEN: On Tuesday, May 30, 2023

WHERE: Huron River Dr Bridge, over the Huron River, between River Pines Dr and Wagner Rd in Scio Township

WHY: Bridge preventative maintenance

BACKGROUND: On Tuesday, May 30, 2023, the Washtenaw County Road Commission (WCRC) will begin preventative maintenance on the Huron River Dr Bridge, over the Huron River, between River Pines Dr and Wagner Rd in Scio Township.

The road will not be closed to traffic, but delays are likely due to intermittent lane closures. WCRC encourages motorists, emergency services and others to use an alternate route.

The bridge work is expected to take approximately two weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org

ISSUE DATE: 05/25/23