Crane Road Chipseal

Location of roadwork:
Between Textile Road and Morgan Road

Township:
Pittsfield

When is the work being done:
Chip seal: Week of 5/31, Fog seal: Week of July 26

Description of work:
Chipseal

Impact on Traffic:
Daytime road closure

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage

Latest Updates

June 1, 2021 Daytime Road Closure: Crane Rd (Pittsfield Twp)

WHEN: Starting on Tuesday, June 1, 2021

WHERE: Crane Rd between Textile Rd and US-12 in Pittsfield Township

WHY: Preventative maintenance – chip seal

BACKGROUND: Starting on Tuesday, June 1, 2021, the Washtenaw County Road Commission (WCRC) will begin a preventative maintenance chip seal project on Crane Rd between Textile Rd and US-12 in Pittsfield Township. The road will reopen at the end of each day and remain open until work resumes the following morning.

The work on this road is expected to be completed by the end of the week. However, all dates are tentative and subject to change due to weather conditions.

Once the work is completed, drivers are advised to lower their speeds to 35 mph while the stone settles.

WCRC will return to this area in a few weeks to apply a fog seal on top of the chip seal and place permanent pavement markings.

CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, (734) 327-6696 or via email at harrisk@wcroads.org.

ISSUE DATE: 06/01/21

Contact information:
Ken Harris
    • (734)-327-6696