Cavanaugh Lake Road Bridge

Location of roadwork:
Over Mill Creek, between Deerfield Ct and Campolina Street

Township:
Sylvan

When is the work being done:
Road reopened 9/2

Description of work:
Bridge Replacement

Impact on Traffic:
Road closed between Deerfield Ct and Campolina Rd with posted detour

Funding Source(s):
Federal, Michigan Transportation Fund (MTF)

Latest Updates

September 2, 2020 Road Reopened: Cavanaugh Lake Road (Sylvan Twp)

WHEN: Wednesday, September 2, 2020

WHERE: Cavanaugh Lake Road between Deerfield Court and Campolina Street in Sylvan Township

WHY: Completion of bridge replacement project

BACKGROUND: On Wednesday, September 2, 2020, at approximately noon, the Washtenaw County Road Commission (WCRC) re-opened Cavanaugh Lake Road between Deerfield Court and Campolina Street in Sylvan Township.

CONTACT: If you have any questions concerning this project, please contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org.

ISSUE DATE: 09/02/20

August 25, 2020 Cavanaugh Lake Rd: Another Step Closer

We’re another step closer to reopening Cavanaugh Lake Road in Sylvan Township. Last week, our contractors placed the “riprap” stones along the new culvert to help prevent erosion and they placed gravel shoulders along the roadside. Next up is more slope restoration work this week and guardrail installation. We are hoping to reopen the road in the next week or two if the weather continues to cooperate.

Until then, the road remains closed to all traffic. If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of riprap installed at Cavanaugh Lake Rd bridge

August 18, 2020 Cavanaugh Lake Rd: Approaching the End

It is paving week on the Cavanaugh Lake Road bridge replacement project in Sylvan Township! Our contractors placed the asphalt road approaches yesterday and will place the gravel shoulders soon.

We are getting closer but the road remains closed to all traffic. We need to install guardrail, apply pavement markings and place permanent signs before the road can be reopened.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

 

photo of new road approaches

August 11, 2020 Cavanaugh Lake Rd: Deck Work

It has been a very productive few weeks on the Cavanaugh Lake Road bridge replacement project in Sylvan Township. Our contractor poured the concrete bridge deck last week. As the concrete continues to cure, our contractor has started the prep work for the asphalt road approaches.

Once the approaches have been completed, we still need to place gravel shoulders, install the guardrail and apply pavement markings before the road can be reopened.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of new bridge deck

The concrete bridge deck was placed last week and continues to cure.

July 29, 2020 Cavanaugh Lake Rd: In with the New

We continue to make steady progress on the Cavanaugh Lake Road bridge replacement project in Sylvan Township. Last week, our contractors demo’d the old structure and placed the new aluminum box culvert. This week they are placing the wingwalls on each end of the new structure and backfilling the area in preparation for the road subgrade and concrete pavement.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of wing walls placed on bridgephoto of wingwalls in place on bridge

July 22, 2020 Cavanaugh Lake Rd: Out with the Old

This week is demolition week on the Cavanaugh Lake Road bridge replacement project in Sylvan Township. Our contractor began dismantling the existing bridge yesterday. Once the old bridge is completely removed, our contractor will begin preparing the area for the new structure.

As a reminder, the road is closed to all traffic during construction including bicycles and pedestrians. Trespassing on the railroad tracks is not ever permissible and is very dangerous. This action could result in a misdemeanor punishable with jail time and/or a fine.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

photo of Cavanaugh Lake Rd bridge demo

Our contractor began removing the existing structure this week.

July 15, 2020 Cavanaugh Lake Rd: Putting the Pieces Together

Our contractor is already making good progress on the bridge replacement on Cavanaugh Lake Road  in Sylvan Township.  They began assembling the new box culvert this week and soon they will demolish the existing bridge.

As a reminder, the road is closed to all traffic during construction including bicycles and pedestrians. Trespassing on the railroad tracks is not ever permissible and could result in a misdemeanor punishable with jail time and/or a fine.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

Culvert Construction at Cavanaugh Lake Rd in Sylvan Township

July 8, 2020 Cavanaugh Lake Rd: Getting Started

Cavanaugh Lake Road between Deerfield Court and Campolina Road in Sylvan Township is officially closed for a bridge replacement project. The road is closed to all traffic for approximately 3 months and a detour is posted.

If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

bridge closure. Sylvan Twp

July 1, 2020 Cavanaugh Lake Rd: Closure Starts July 8

WHEN: Starting Wednesday, July 8, 2020

WHERE: Cavanaugh Lake Road between Deerfield Court and Campolina Street in Sylvan Township

WHY: Bridge replacement

BACKGROUND: Starting Wednesday, July 8, 2020, the Washtenaw County Road Commission (WCRC) will close Cavanaugh Lake Road between Deerfield Court and Campolina Street in Sylvan Township to replace the bridge over Mill Creek.

The road will be closed for approximately 3 months. However, all dates are tentative and subject to change due to weather conditions.

DETOUR: Click here for the detour map

CONTACT: If you have any questions concerning this work, please contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, or via email at murphyn@wcroads.org.

ISSUE DATE: 07/01/20

June 22, 2020 Cavanaugh Lake Rd: Closure Expected Early-July

It is nearly time for us to begin the bridge replacement project on Cavanaugh Lake Road over Mill Creek in Sylvan Township. Our contractor is making preparations to close Cavanaugh Lake Road between Deerfield Ct and Campolina Rd in early-July. Once construction begins, the road will be closed to all traffic for approximately 3 months and a detour will be posted.

Digital message boards will be placed near the project area in advance of the road closure and we will issue an advisory once an exact start date has been determined.

If you have any additional questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

February 12, 2020 Cavanaugh Lake Road: Start Date Pushed to July

Unfortunately, due to continued delays from the railroad in granting required permissions to work within the railroad right-of-way, along with environmental restrictions at the site, the Cavanaugh Lake Road Bridge Project has been postponed to July 2020.  July is the earliest we can begin due to environmental restrictions on the stream that are in effect April – June.

The new plan is to close the road after the Fourth of July holiday weekend. The road will be closed for approximately 3 months while we replace the bridge.

There will be a pause in project update emails until we get closer to the road closure. A road closure advisory will be emailed and digital message boards will be placed near the project area in advance of the road closure.

Thanks for your patience during this process. If you have any additional questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

Click here to visit the project page and subscribe to receive project updates via email.

January 28, 2020 Cavanaugh Lake Road: Start Date Still TBD

Unfortunately, our contractor is still waiting for all the necessary permissions needed to work within the railroad right-of-way on the Cavanaugh Lake Road Project in Sylvan Township. We are hoping to begin construction sometime in February. A road closure advisory will be emailed and digital message boards will be placed near the project area in advance of the road closure.

If you have any additional questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org
December 18, 2019 Construction to Begin in New Year
At this time, we expect construction on the Cavanaugh Lake Road Project in Sylvan Township to begin in early-January 2020. Our contractor continues to work with the railroad owner to receive the proper permissions needed to work within the railroad right-of-way.

A road closure advisory will be emailed and digital message boards will be placed near the project area in advance of the road closure.

If you have any additional questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org
November 1, 2019 Construction Open House: Cavanaugh Lk Rd (Sylvan Twp)

WHAT:  Cavanaugh Lake Road Bridge Construction Open House

WHEN: Thursday, November 14, 2019 from 6:30 – 7:30 p.m.

WHERE: Chelsea District Library, 221 S. Main Street, Chelsea

WHY: The Washtenaw County Road Commission (WCRC) will hold a construction open house on Thursday, November 14, 2019 from 6:30 – 7:30 p.m. to provide information and answer questions about the project planned on Cavanaugh Lake Road in Sylvan Township this fall/winter.

WCRC will replace the bridge over Mill Creek between Deerfield Court and Campolina Road in Sylvan Township beginning in late November. The bridge will be closed to all traffic until February 2020.

CONTACT: Visit www.wcroads.org/wcrc-project/cavanaugh-lake-road-culvert/ for more information. If you have any questions, please contact Nate Murphy, project manager, (734) 327-6647, murphyn@wcroads.org.

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being considered at the meeting, to individuals with disabilities upon a 7-business day notice to WCRC. Individuals with disabilities requiring auxiliary aids or services should contact Emily Kizer, communications manager, by phone (734) 327-6646, by email kizere@wcroads.org, by fax (734) 761-3737 or by mail at WCRC, 555 N. Zeeb Road, Ann Arbor, MI 48103.

ISSUE DATE: 11/01/2019

Contact information:
Nate Murphy
    • (734) 327-6647
Receive Updates on the Project