Campus Parkway

Location of roadwork:
Community Drive to Industrial Drive

Township:
Pittsfield

When is the work being done:
08/22 - 08/27

Description of work:
Mill & Resurfacing

Impact on Traffic:
Intermittent Lane Closure

Funding Source(s):
Supplemental State Funding

Latest Updates

August 26, 2019 Lane Restrictions: Campus Parkway (Pittsfield Twp)

WHEN: Starting Thursday, August 29, 2019

WHERE: Campus Parkway between Industrial Drive and Community Drive in Pittsfield Township

WHY: Road resurfacing

BACKGROUND:  On Thursday, August 29, 2019, the Washtenaw County Road Commission (WCRC) will begin a road resurfacing project on Campus Parkway between Industrial Drive and Community Drive in Pittsfield Township.

The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC is coordinating with Saline Community Schools to minimize the impact but there will be some delays to school traffic during this project.

The road improvements are expected to take approximately six days. However, all dates are tentative and subject to change due to weather conditions.

Sidewalks and crossing signals will not be impacted by this work.

CONTACT: If you have any questions concerning this project, please contact Mike Bernbeck, (734) 327-6654, or via email at bernbeckm@wcroads.org

ISSUE DATE: 08/26/19

Contact information:
Mike Bernbeck
    • (734) 327-6654