This project represents a partnership between the Washtenaw County Parks and Recreation Commission, the Huron Clinton Metroparks and the Huron Waterloo Pathways Initiative. WCRC is involved to administer a federal Transportation Alternative Program grant that is helping to fund this project.
Location of roadwork:
Along the Huron River between Zeeb Rd and Delhi Metropark
Township:
Scio
When is the work being done:
Pathway construction: Fall 2022 - Fall 2023
Description of work:
Non-Motorized Path Construction
Impact on Traffic:
Intermittent shoulder closures and two short-term road closures for culvert replacements
Funding Source(s):
Transportation Alternatives Program (TAP), Washtenaw County Parks and Recreation Commission
Latest Updates
Construction is expected to resume on the D-3 section of the Border-to-Border (B2B) pathway along the Huron River in Scio Township, Spring 2023!
A contractor for Washtenaw County Roads Commission will continue to work on the retaining wall structures and begin constructing the bridge over the Huron River. However, due to the time required for fabrication and coordination with the railroad company, the bridge erection schedule is undetermined.
During the 2022 construction season, our contractor graded the projected path, installed drainage structures, and began construction on two retaining walls.
Motorists will begin to see construction signs at this location Spring of 2023. WCRC will send out a notice to inform the public of potential impacts.
Questions? Contact Michele Ford, project manager, (734) 327-6652, or via email at fordm@wcroads.org
Pictured above is the graded pathway of the D3 section of the Border-to-border trail in Scio Township!
This project represents a partnership between the Washtenaw County Parks and Recreation Commission, the Huron Clinton Metroparks and the Huron Waterloo Pathways Initiative. WCRC is involved to administer a federal Transportation Alternative Program grant that is helping to fund this project.
WHEN: Starting Wednesday, October 12, 2022
WHERE: Huron River Dr between Zeeb Rd and Delhi Rd in Scio Township
BACKGROUND: On Wednesday, October 12, 2022, a contractor for the Washtenaw County Road Commission (WCRC) will close one lane on Huron River Dr between Zeeb Rd and Delhi Rd in Scio Township as a part of Segment D3 construction on the Border-to-Border pathway project.
The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.
The lane closure is expected to last approximately 3 days. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Michele Ford, project manager, (734) 327-6652, or via email at fordm@wcroads.org
ISSUE DATE: 10/10/22
We’re planning to start construction next week on section D3 of the Border-to-Border (B2B) pathway along the Huron River in Scio Township. We have all the necessary permits and our contractor is ready to go.
To get started, our contractor will build a temporary construction driveway on Huron River Dr, west of Delhi MetroPark. They will also prepare the work site for earthwork. Nearly all of this early earthwork will take place well away from the road and won’t impact traffic.
Due to the complexity of this construction, the pathway is expected to take more than a year to complete. When completed, this segment will run from the intersection of Zeeb Rd and Huron River Dr to Delhi Metropark.
Questions? Contact Michele Ford, project manager, fordm@wcroads.org, (734) 327-6652.
This project represents a partnership between the Washtenaw County Parks and Recreation Commission, the Huron Clinton Metroparks and the Huron Waterloo Pathways Initiative. WCRC is involved to administer a federal Transportation Alternative Program grant that is helping to fund this project.
Good news…construction is expected to begin soon on section D3 of the Border-to-Border (B2B) pathway along the Huron River in Scio Township. After months of working through a complex design and permitting process, our contractor is expected to begin earthwork in the coming weeks.
This trail project begins at the intersection of Zeeb Rd and Huron River Dr and ends in Delhi Metropark (1.1 miles), joining two previously completed sections of B2B Trail. The trail is on the south side of Huron River Dr and within the road and railroad rights-of-way before crossing the Huron River and entering Delhi Metropark. The trail work includes grading, paving of an asphalt trail, construction of retaining walls, installation of a pedestrian bridge over the Huron River, turf restoration and plantings, and other related improvements.
Initially, there will not be any significant impact to motorists, most of the pathway construction will take place away from the road. However, later this year, there will be brief closures on Zeeb Rd near Huron River Dr and Huron River Dr between Preserve Dr and Greenook Dr as we install two crossroad culverts. We will post an advisory in advance of these closures.
Due to the complexity of this construction, the pathway is expected to take more than a year to complete.
Questions? Contact Michele Ford, project manager, fordm@wcroads.org, (734) 327-6652.
This project represents a partnership between the Washtenaw County Parks and Recreation Commission, the Huron Clinton Metroparks and the Huron Waterloo Pathways Initiative. WCRC is involved to administer a federal Transportation Alternative Program grant that is helping to fund this project.
WHAT: Public Information Meeting regarding Border-to-Border Trail projects
WHEN: Monday, February 1, 2021 from 7 p.m. to 8 p.m.
WHERE: https://us02web.zoom.us/j/86959262637 To join use a web browser to visit zoom.us, click “Join a Meeting” and enter the following information: Webinar ID: 869 5926 2637
WHO: Hosted by the Washtenaw County Parks and Recreation Commission in partnership with the Washtenaw County Road Commission, Huron Clinton Metroparks and Huron Waterloo Pathways Initiative
WHY: This public informational meeting will discuss an upcoming Border-to-Border Trail (B2B) project between Zeeb Road and Delhi Metropark in Scio Township. The meeting will be virtual via Zoom and will consist of a presentation followed by discussion question and answer session.
CONTACT: If you have any questions concerning this project, please contact Peter Sanderson, Park Planner at the Washtenaw County Parks and Recreation Commission via email at sandersonp@washtenaw.org
Washtenaw County will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audio of printed materials being considered at the meeting, to individuals with disabilities at the meeting upon 7-day notice to Washtenaw County. Individuals requiring auxiliary aids or services should contact the County of Washtenaw by writing or calling the following: Human Resources, 734-994-2410, TTD# 734/994-1733.
ISSUE DATE: January 19, 2021