Ann Arbor-Saline Road and Wagner Road

Location of roadwork:
Intersection of Ann Arbor-Saline Road and Wagner Road

Township:
Lodi

When is the work being done:
Intersection reopened on 6/10/2020

Description of work:
Add Center Left-Turn Lane, Drainage Improvements, Install Traffic Signal, Road Reconstruction

Impact on Traffic:
Intersection will be closed to traffic for approximately 3 months during construction

Funding Source(s):
Michigan Transportation Fund (MTF)

Latest Updates

July 9, 2020 Lane Restrictions: Ann Arbor-Saline Road and Wagner Road (Lodi Twp)

WHEN: Friday, July 10, 2020

WHERE: Intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township

WHY: Asphalt repair

BACKGROUND: On Friday, July 10, 2020, the Washtenaw County Road Commission’s contractor will repair some pavement defects at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township.

The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The new traffic signal at this intersection will be in flash mode to help facilitate lane restrictions. It will return to the normal cycle once the work has been completed.

The repairs are expected to take approximately one day. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, (734) 327-6648, or via email at berkholza@wcroads.org

ISSUE DATE: 07/09/20

June 18, 2020 Ann Arbor-Saline Rd and Wagner Rd: Pavement Defeats Will Be Fixed

Last week, we reopened the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. Unfortunately, since the reopening, we have discovered pavement defects in some of the freshly placed asphalt. This type of defect isn’t very common but unfortunately can happen.

Our crews will continue to monitor and patch the defected area until permanent repairs can be made by our contractor. Since we are already planning to return to Lodi Township this fall to finish resurfacing Pleasant Lake Road between Zeeb Road and Wagner Road, our preliminary plan is to pair permanent repairs on Ann Arbor-Saline Road with the paving planned on Pleasant Lake Road.

We will provide a more detailed schedule as we get closer.

If you have any questions about this work, please contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.

June 10, 2020 Road Reopened: Ann Arbor-Saline Rd and Wagner Rd (Lodi Twp)

WHEN: Effective Wednesday, June 10, 2020

WHERE: Intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township

WHY: Completion of intersection improvement project

BACKGROUND:  On Wednesday, June 10, 2020, at approximately 8:15 a.m., the Washtenaw County Road Commission (WCRC) re-opened the Intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township after completing an improvement project.

The new traffic signal will be in “flash” mode for a few days and should be treated as a three-way stop. The signal will switch to it’s normal “red – yellow – green” cycle soon.

CONTACT: If you have any questions concerning this project, please contact Michele Ford, (734) 327-6652, fordm@wcroads.org

ISSUE DATE: 06/10/20

June 8, 2020 Ann Arbor-Saline Rd and Wagner Rd: Getting Close

We continue to make steady progress on our project at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. We have a few items to finish before the intersection can be reopened to traffic, including pavement markings and final signal work. We are hoping to have it reopened in the next week or so if the weather cooperates.

Thank you for your patience. If you have questions about the project, please contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.

May 26, 2020 Ann Arbor-Saline Rd and Wagner Rd: Paving Has Begun

After a tough start to the month, we’ve made great progress in the past couple of weeks at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. The damaged concrete was removed and replaced. Our contractor paved the first layer of asphalt last week. We are hoping to apply the second layer this week if the weather cooperates. We have also started to install the traffic signal.

While we have made great progress, we still have some important items to finish before we can safely reopen the road, including placing gravel shoulders, installing pavement markings and placing permanent signs.

The intersection remains closed, please continue to stay out of the work zone for your safety and the safety of those working on site.

Paving on Ann Arbor-Saline Rd and Wagner Rd

Our contractor placed the first layer of asphalt last week.

To help prevent the spread of the coronavirus (COVID-19), our employees and contractors are instructed to practice social distancing while on the job site. If you have questions about the project, please do not approach staff in the field. Instead, contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.

 

May 6, 2020 Ann Arbor-Saline Rd and Wagner Rd: We Need Your Help

This week, we started pouring concrete pavement at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. We were making great progress but unfortunately, last night someone maliciously drove through the work zone and damaged much of the fresh concrete.

The damage will delay the project by at least a week and is estimated to cost about $20,000 to remove and replace.

This terrible act is being investigated by the Washtenaw County Sheriff’s Office. They believe that the tire impressions are from an all-terrain type vehicle that appears to be pulling a trailer. If you have any information, please contact the Washtenaw County Sheriff’s Office at (734) 994-2911.

We know that any road closure is frustrating but we ask that you please obey the signs and barricades. We have closed the intersection for your safety, the safety of our workers and to protect the road infrastructure we are building. Concrete takes time to cure and as we saw last night, cannot be driven, biked or walked on until it has properly cured. Please help us by staying out of the work zone.

post from Washtenaw County Sheriff Dept.

May 4, 2020 Ann Arbor-Saline Rd and Wagner Rd: Time for Concrete!

We continue to make steady progress on our project at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township.

Today, our contractor started pouring concrete pavement and this work will continue throughout this week. Once the concrete has been poured, it takes days to get to full traffic-bearing strength. Vehicles of all kinds must stay out of the work zone. Driving across the newly placed concrete pavement will damage it beyond repair and result in the removal of that concrete, extending the duration of the current closure. Moreover, entering the work zone is hazardous for both motorists and road workers.

Once the concrete has cured, our contractor will continue to prepare the roadbed north and south of the intersection for asphalt paving.

To help prevent the spread of the coronavirus (COVID-19), our employees and contractors are instructed to practice social distancing while on the job site. If you have questions about the project, please do not approach staff in the field. Instead, contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.

drone photo of Ann Arbor-Saline Rd and Wagner Rd

Drone shot of the intersection of Ann Arbor-Saline Rd and Wagner Rd last Friday. Contractors began pouring concrete today.

April 22, 2020 Ann Arbor-Saline Road and Wagner Road: Placing Curb
Despite the gray spring weather, we continue to make progress on the improvement project at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. Earlier this week, our contractor finished installing the storm sewer and today, they started pouring concrete curb. Once they finish pouring the curb and the concrete has cured to sufficient strength, they have some additional earthwork to complete before concrete pavement can be poured.
To help prevent the spread of the coronavirus (COVID-19), our employees and contractors are instructed to practice social distancing while on the job site. If you have questions about the project, please do not approach staff in the field. Instead, contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.
Curb going in on Ann Arbor-Saline Rd

Our contractors began pouring concrete curb today on Ann Arbor-Saline Road.

April 14, 2020 Ann Arbor-Saline Road and Wagner Road: Storming Along

Our contractor continues to make steady progress on the improvement project at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township. So far, they have removed all the existing pavement and are working to place the new storm sewer. In addition, they have started to grade the roadbed in preparation for the aggregate base. We are hoping they can start pouring the concrete curb soon.

To help prevent the spread of the coronavirus (COVID-19), our employees and contractors are instructed to practice social distancing while on the job site. If you have questions about the project, please do not approach staff in the field. Instead, contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org.

Grading work on Ann Arbor-Saline Rd and Wagner Rd

Our contractor has started grading the roadbed at the intersection of Ann Arbor-Saline Road and Wagner Road in preparation for aggregate.

 

March 24, 2020 Ann Arbor-Saline Road and Wagner Road: Intersection Closed

Under Governor Whitmer’s Stay Home, Stay Safe, Save Lives Executive Order, road construction projects have been deemed “critical infrastructure work” and will continue as scheduled.

This morning our contractor closed the intersection of Ann Arbor-Saline Road and Wagner Road to begin the scheduled intersection improvement project. The intersection will be closed for approximately 3 months. Residents and property owners who live within the work zone will be provided access to their properties but all other traffic needs to use the posted detour or seek an alternate route. Click here for the detour map. 

In an effort to help prevent the spread of the coronavirus (COVID-19), we have instructed our employees and contractors to practice social distancing while on the job site. If you have questions about the project, please do not approach staff in the field. Instead, contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org

 

March 19, 2020 Road Closure Advisory: Intersection of Ann Arbor-Saline Road and Wagner Road (Lodi Twp)

WHEN: Starting Monday, March 23, 2020

WHERE: The intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township.

WHY: Intersection improvement project

BACKGROUND: Starting Monday, March 23, 2020, the Washtenaw County Road Commission (WCRC) and its contractor will close the intersection Ann Arbor-Saline Road and Wagner Road in Lodi Township for an intersection improvement project.

The intersection will be closed to traffic for approximately 3 months. All individuals who live or work within the construction area will be provided access to their property by the contractor during construction. All other traffic will be required to follow the posted detour or seek an alternative route.

Local businesses will remain open during construction.

DETOUR: Click here for the detour map.

CONTACT: If you have any questions concerning this work, click here to visit the project web page or contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org

ISSUE DATE: 03/19/20

March 13, 2020 Ann Arbor-Saline Rd and Wagner Rd: Closure to Start on March 23

If the weather cooperates, our contractor is planning to begin construction at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township on Monday, March 23, 2020. The road will be closed to through-traffic for approximately 3 months once construction begins.

Local businesses will remain open during construction.

For specific questions about this project contact Michele Ford, project manager, at (734) 327-6652 or fordm@wcroads.org.

March 6, 2020 Ann Arbor-Saline Rd and Wagner Rd: Project to Begin Soon

Tree removals at the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township have been completed, there are a few more stumps to be ground down but that work will take place later this month. Our contractor is planning to start construction in mid-March. The exact date depends on the lifting of seasonal weight restrictions which is completely weather dependent.

Once the intersection is closed, it will be closed to all through-traffic for approximately 3 months and a detour will be posted. Local businesses will remain open during this project.

For specific questions about this project contact Michele Ford, project manager, at (734) 327-6652 or fordm@wcroads.org.

February 14, 2020 Lane Restrictions: Ann Arbor-Saline Rd and Wagner Rd (Lodi Twp)

WHEN: Starting Tuesday, February 18, 2020

WHERE: The intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township.

WHY: Tree removals

BACKGROUND: Starting Tuesday, February 18, 2020, the Washtenaw County Road Commission (WCRC) and its contractor will begin tree removals at the intersection Ann Arbor-Saline Road and Wagner Road in Lodi Township. These removals are in preparation for the intersection improvement project that will take place this spring/summer.

The intersection will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The tree work is expected to take approximately one week. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Michele Ford, project manager, (734) 327-6652, or via email at fordm@wcroads.org

ISSUE DATE: 02/14/20

January 28, 2020 Ann Arbor-Saline Road and Wagner Road: Tree Removals to Begin Soon

Later this year, we will reconstruct the intersection of Ann Arbor-Saline Road and Wagner Road in Lodi Township to include a new traffic signal, concrete pavement, drainage improvements, and dedicated turn lanes.

In preparation for this work, our contractor will begin the necessary tree removals in the coming weeks. We are planning to remove approximately 25 trees that are in conflict with the planned improvements. The intersection will remain open to traffic during the tree work but there may be lane restrictions. We will issue a road advisory ahead of these lane restrictions. All tree removal work will be completed by March 31, 2020.

For specific questions about this project contact Michele Ford, project manager, at (734) 327-6652 or fordm@wcroads.org.

June 13, 2019 June 11 Open House Summary

In summary, we will complete the following work on Ann Arbor-Saline Road in Pittsfield and Lodi Townships:

  • Ann Arbor-Saline Road at Wagner Road Intersection
  • Ann Arbor-Saline Road at Pleasant Lake Road Intersection
    • Upgrade the existing traffic signal to include left turn protection. This intersection will remain open to traffic during construction but there will be intermittent lane restrictions.
  • Ann Arbor-Saline Road Concrete Repairs

After listening to resident feedback at the June 11 project open house, we will instruct the contractor that the Ann Arbor-Saline Road and Wagner Road project must take place in the spring of 2020. The concrete repair work on Ann Arbor-Saline Road near I-94 may still take place this fall (between home U of M football games) or during the spring of 2020. We will issue additional updates as we get closer to the start of these projects.

If you have any questions, please contact Michele Ford, civil engineer, phone: (734) 327-6652, fordm@wcroads.org

May 14, 2019 Project Open House: Ann Arbor-Saline Road Improvements

WHAT: Ann Arbor-Saline Road Improvements Open House

WHEN: Tuesday, June 11, 2019 from 6 – 7 p.m.

WHERE: Lodi Township Hall, 3755 Pleasant Lake Road, Ann Arbor, MI 48103

WHY: The Washtenaw County Road Commission (WCRC) will hold an open house on Tuesday, June 11, 2019 at the Lodi Township Hall to share information about the improvements planned for Ann Arbor-Saline Road.

The Ann Arbor-Saline Road at Wagner Road intersection will be reconstructed and signalized, and the existing traffic signal at Ann Arbor-Saline Road and Pleasant Lake Road will be upgraded. In addition, concrete repairs will be made on Ann Arbor-Saline Road between Oak Valley Drive and I-94.

CONTACT: If you have any questions, please contact Michele Ford, (734) 327-6652.

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being considered at the meeting, to individuals with disabilities upon a 7-business day notice to WCRC. Individuals with disabilities requiring auxiliary aids or services should contact Emily Kizer, communications manager, by phone (734) 327-6646, by email kizere@wcroads.org, by fax (734) 761-3737 or by mail at WCRC, 555 N. Zeeb Road, Ann Arbor, MI 48103.

ISSUE DATE: 5/14/2019

May 9, 2019 Project Announcement: Ann Arbor-Saline Road Improvements

The Washtenaw County Road Commission (WCRC) is excited to announce three new projects on Ann Arbor-Saline Road in Lodi and Pittsfield Townships in 2019.

Here’s a summary of the planned improvements:

  • Ann Arbor-Saline Road at Wagner Road Intersection
    • Reconstruct the intersection to include concrete pavement, drainage improvements, and dedicated turn lanes, and install a traffic signal to optimize traffic movements. The intersection will be closed for approximately three months during this project.
  • Ann Arbor-Saline Road at Pleasant Lake Road Intersection
    • Upgrade the existing traffic signal to include left turn protection signalization and signal timing optimization. This intersection will remain open to traffic during construction but there will be intermittent lane restrictions.
  • Ann Arbor-Saline Road Concrete Repairs
    • Replace existing damaged concrete overlay with full-depth concrete pavement in various locations between Oak Valley Drive and the I-94 ramps. The road will be closed in segments during this project but the intersections will remain open to traffic.

The work is expected to take place later in the 2019 or early in the 2020 construction season. WCRC will hold an open house about all three projects on Tuesday, June 11, 2019 from 6 – 7 p.m. at the Lodi Township Hall, 3755 Pleasant Lake Rd, Ann Arbor.

WCRC will post project updates and road advisories online at www.wcroads.org and on its Facebook and Twitter pages. Subscribe to project updates and road work advisories: www.wcroads.org/residents/subscribe-to-road-updates/ For specific questions on this project, contact Michele Ford, Civil Engineer, at (734) 327-6652 or fordm@wcroads.org.

Contact information:
Michele Ford
    • (734) 327-6652
Receive Updates on the Project
Subscribe to Project Updates