WHEN: Wednesday, July 26, 2023
WHERE: N. Territorial Rd between Huron River Dr and Mast Rd in Webster Township
WHY: Preventative maintenance – fog seal
BACKGROUND: On Wednesday, July 26, 2023, the Washtenaw County Road Commission (WCRC) will continue a preventative maintenance fog seal project on N. Territorial Rd between Huron River Dr and Mast Rd in Webster Township.
The roadwork is expected to take approximately one day to complete. However, all dates are tentative and subject to change due to weather conditions.
Fog seal is another thin layer of liquid asphalt placed on top of a recent chip seal that helps to seal in the chips and further protect the pavement.
The work will be conducted under a combination of lane restrictions and daytime closures to allow the fog seal to cure. A contractor for WCRC will return to this area in a few weeks to place permanent pavement markings.
CONTACT: If you have any questions, please contact Ken Harris, superintendent of maintenance, at (734) 327-6696 or via email at [email protected].
ISSUE DATE: 07/26/23