The weather is finally cooperating on the Leforge Rd Resurfacing Project in Superior Township! We plan to finish paving by this evening. Our contractor hopes to finish the following final…
Cavanaugh Lake Rd in Sylvan Township has been open for a few days now and is looking good! We’re still waiting for the final application of pavement markings which will…
Good morning, It’s hard to believe but we’re just one week away from our Fall Employee Appreciation Breakfast (aka Pancake Breakfast)! Here’s a general summary of the event… Date: Friday,…
Despite a very rainy few days, we continue to make progress preparing for the Huron River Dr Road Resurfacing Project on the border of Dexter and Webster Townships. Our crews…
WHEN: Starting Friday, October 21, 2022 WHERE: Packard Rd between US-23 and Carpenter Rd in Pittsfield Township WHY: Permit work: DTE structure adjustment BACKGROUND: On Friday, October 21, 2022, a…
WHEN: On Wednesday, October 19, 2022 WHERE: Cavanaugh Lake Rd between Pierce Rd and The City of Chelsea in Sylvan Township WHY: Road resurfacing BACKGROUND: On Wednesday, October 19, 2022,…
Things are looking really good on our Cavanaugh Lake Rd Resurfacing Project in Sylvan Township. Our contractor finished paving over the weekend and we are now waiting for a weather…
So far, paving is going smoothly on the Cavanaugh Lake Rd Resurfacing Project in Sylvan Township. Today, our contractor started placing the second layer of asphalt aka wearing course. We…
Good afternoon, As October flies by, we continue to get ready for winter. In Operations, four more crews completed their Dry Run inspections this week, while other crews started their…
Good news on the Cavanaugh Lake Rd Resurfacing Project in Sylvan Township…Our contractor’s schedule has moved around and we are now planning to start paving tomorrow! Our contractor will start…