was successfully added to your cart.

Textile Road

Location of roadwork:
State Road to Michigan Avenue

Township:
Pittsfield

When is the work being done:
Construction will take place June 18 through mid-November

Description of work:
Non-Motorized Path Construction, Paving, Road Reconstruction

Impact on Traffic:
Full closure to through-traffic between Hines Drive and Michigan Avenue

Funding Source(s):
Federal, Four-Year Road and Non-Motorized Path Millage, Michigan Transportation Fund (MTF), Township

Latest Updates

July 3, 2018 Road Closure: Textile Road and Platt Road Intersection (Pittsfield Twp)

WHEN: Starting Wednesday, July 11

WHERE: Intersection of Platt Road and Textile Road in Pittsfield Township

WHY: Intersection reconstruction

BACKGROUND: On Wednesday, July 11, 2018, the Washtenaw County Road Commission (WCRC) and its contractor will close the intersection of Platt Road and Textile Road in Pittsfield Township to reconstruct the intersection. This work is a part of the reconstruction of Textile Road that is currently underway.

The intersection will be closed to all through traffic and a detour will be posted.

The intersection is expected to be reopened by Wednesday, August 8, 2018. However, please be advised that all dates are tentative and subject to change due to weather conditions.

CONTACT: Questions concerning the project should be directed to:

For more information about WCRC road closures visit wcroads.org/news/media-advisories.

ISSUE DATE: 07/03/18

June 27, 2018 Textile Road Local Traffic Update

Good news! We made the necessary repair between Hines Drive and the Ann Arbor Railroad earlier this afternoon. That section of Textile Road is back open to local traffic (those who live or work within the construction zone). Textile Road from Hines Drive to Michigan Avenue remains closed to all through-traffic.

During the next couple of weeks, as we progress down the road with the storm sewer, we will have more temporary local traffic closures like this one. We will send an email update ahead of these closures whenever possible.

Tomorrow, June 28, 2018, is the next local traffic closure. We will be temporarily closing Textile Road to local traffic between Marton Road and Campbell Road while we work. If you live or work within this area, you will still be able to access or your home or workplace but you will need to use side roads since no traffic can traverse the closure.

Thanks for your patience!

As always, please contact Mark McCulloch, project manager if you have any questions – mccullochm@wcroads.org or (734) 327-6679.

June 26, 2018 Textile Road – Temporary closure to all traffic

We’re one week into our full closure of Textile Road and the project is progressing pretty well, utilities are working on relocating their facilities and our road contractor is working on the storm sewer.

Unfortunately, we have run into an unexpected drainage issue between Hines Drive and the Ann Arbor Railroad that we need to fix. This means that Textile Road will be closed to all traffic, including local traffic, tomorrow, Wednesday, June 27, between Hines Drive and the Ann Arbor Railroad. If you live or work between Hines Drive and the railroad crossing, you will still be able to access or your home or workplace but you will need to use side roads since no traffic can traverse this closure.

We hope to fix this issue sometime tomorrow and reopen this section to local traffic only, as long as the weather cooperates. If it rains tomorrow, we may not be able to make all the repairs until Thursday. We will send you another email update if we have to extend the closure.

As always, please contact Mark McCulloch, project manager if you have any questions – mccullochm@wcroads.org or (734) 327-6679.

June 11, 2018 Textile Road Full Closure to Begin June 18

The full closure of Textile Road between Hines Drive and Michigan Avenue (US-12) in Pittsfield Township is scheduled to begin on Monday, June 18.

When the full closure begins, Textile Road from Hines Drive to Michigan Avenue will only be open to property owners and tenants. People who do not live or own property internal to the project limits will be required to follow posted detour routes or seek an alternate route while work is occurring.

The goal is to have Textile Road reopened to traffic by mid-November.

Questions?

March 27, 2018 Textile Road and Platt-Textile Greenway: Preliminary Work to Continue

Tree removals have been completed for both Textile Road and the Platt-Textile Greenway. Utility relocation work will continue throughout the spring.

Construction to build the roadway and greenway will begin on or after June 18, 2018.  During construction, Textile Road between Hines Drive and Michigan Avenue (US-12) will be closed to through traffic.

If you have any questions concerning this project, please contact Mark McCulloch, Senior Project Manager, Washtenaw County Road Commission, (734) 327-6679 or mccullochm@wcroads.org

February 16, 2018 Textile Road and Platt-Textile Greenway: Preliminary Work to Begin

WHEN: Monday, February 19, 2018

WHERE: Textile Road between Hines Drive and Michigan Avenue (U.S. 12) in Pittsfield Township

WHY: Textile Road Paving and Platt-Textile Greenway

BACKGROUND: Starting Monday, February 19, 2018, tree removal and site clearing work will begin for the upcoming Textile Road and Platt-Textile Greenway project. The tree removal work will occur along Textile Road between Hines Drive and Michigan Avenue (U.S. 12) in Pittsfield Township and is expected to last up to two weeks.

Construction to build the roadway and greenway will begin in June of this year.   

CONTACT: If you have any questions concerning this project, please contact Mark McCulloch, Senior Project Manager, Washtenaw County Road Commission, (734) 327-6679 or mccullochm@wcroads.org

ISSUE DATE: 02/16/18

January 17, 2018 Feb. 8 Construction Information Meeting – Textile Rd

The Washtenaw County Road Commission (WCRC) will be paving Textile Road from Hines Drive to Michigan Avenue (U.S. 12).

The community is invited to a construction information meeting on Thursday, February 8 at 6:30 p.m. at the Pittsfield Township Hall, 6201 W. Michigan Avenue, Ann Arbor, MI 48108. WCRC staff will be in attendance to share construction details.

During this project WCRC and its contractors will also:

  • In partnership with Pittsfield Township, build the Platt-Textile Greenway, a 1.3 mile non-motorized pathway, which will connect Marsh View Meadows Park to the existing non-motorized pathway running north-south along Platt Road.
  • Replace culverts at the Koch-Warner and Pittsfield No. 5 Drains.
  • Install new traffic signals at the intersections of Textile Road/Michigan Avenue and Textile/Platt Roads.
  • Construct center left-turn lanes at the intersection of Platt/Textile Roads.
  • Resurface pavement from State Road to the end of existing pavement.
  • Install new railroad crossing guards with warning lights at the train tracks.
  • Pave the Old Hickory Trail Parking lot.

Project Timeline:

Tree removal will likely occur in February and March. All other work will begin on or after June 18, 2018. Our goal is to complete the project in Mid-November, weather pending.

Detours and Access:

  • When reconstruction works begins in June of 2018, Textile Road from Hines Drive to Michigan Avenue will only be open to property owners and tenants.
  • Marsh View Meadow Park will remain open with access from Marton Road.
  • Non-residents will be required to follow posted detour routes while work is occurring.
  • In addition, sometime between June and October, the intersection of Platt Road and Textile Road will be closed to all traffic for a period of time up to four weeks. WCRC will issue a media advisory the week before this closure.
  • WCRC will coordinate mail delivery and garbage collection during the life of the project.

For more information: