was successfully added to your cart.

Huron River Drive Bridge

Location of roadwork:
Over Pittsfield-Ann Arbor Drain

Township:
Ann Arbor

When is the work being done:
April through July

Description of work:
Bridge Preservation

Impact on Traffic:
Full Closure

Latest Updates

July 20, 2017 Huron River Drive Bridge – Progress Update

The work performed on this bridge so far has included concrete deck repairs, new bridge railing, deck joint replacement, limited new road approach to the bridge, stream erosion repairs, sanitary sewer repairs and new guardrail.  Work remaining to be completed includes an epoxy overlay on the bridge deck, which is expected to occur the week of July 24th.  Huron River Drive is expected to reopen by the end of July, weather permitting.

March 31, 2017

Advisory: Bridge Closure scheduled for 4/10/2017

Detour: Huron Parkway to Geddes Road to Dixboro Road to Hogback Road