This summer, the Washtenaw County Road Commission (WCRC) will be replacing the Sharon Valley Road Bridge over the River Raisin in Sharon Township.

Join WCRC Staff for a construction information meeting on Thursday, June 21 at 6 p.m. at the Sharon Township Hall, 18010 Pleasant Lake Road, Manchester, to learn more about the project.

During this project WCRC and its contractors will:

  • Replace the existing 72-foot bridge over the River Raisin with an 85-foot bridge.
  • Reconstruct the road approaches and install guardrail.

Project Timeline: WCRC’s contractor will begin on July 1, 2018 and will be completed by early October, depending on the weather.

Detours and Access: Sharon Valley Road will be closed throughout construction between Prospect Hill Rd and Lamb Rd, with traffic detoured to Sharon Hollow Road, Austin Road and Wolf Lake Road.

For more information: