Ridge Road Bridge Project Update

By October 16, 2017Uncategorized

The contractor has set the beams in place, poured the concrete bridge deck, poured the concrete bridge approaches, and begun reconstructing the road.  Major items of work remaining to be completed include the completion of the road construction, building the bridge railings, installing guardrail and restoring the site.  The Road Commission has added work to this project to include the reconstruction of Ridge Rd from the bridge project to Mooreville Rd.  This work is currently ongoing.