Our Unpaved Road Improvement project on Joy Rd between Whitmore Lake Rd and Earhart Rd in Ann Arbor & Northfield Townships is moving along.  

Last week, our crews were able to complete the necessary drainage and forestry operations. This week, our crews will begin spreading new limestone throughout the project limits. During the limestone spreading, Joy Rd will continue to be closed during daytime hours to through traffic. Access will continue to be maintained for residents who work or live within the project limits, but please be aware of the limestone piles and potential equipment in the roadway.  

Have questions about the project? Contact Kenneth Harris, Superintendent of Maintenance, at (734) 327-6696 or via email at harrisk@wcroads.org. 

Pictured is the drainage work our crews completed on Joy Rd between Whitmore Lake Rd and Earhart Rd in Ann Arbor & Northfield Townships.