What: Road Closure / Roadway Construction
When: Monday, June 29, 2009
Where: Milan-Oakville Road, Milan City limits to Gooding Road
Why: Construction Start / ROAD CLOSURE
Background
The Washtenaw County Road Commission has scheduled the CLOSURE of Milan-Oakville Road, between the Milan City limits and Gooding Road, beginning on Monday, June 29, 2009. This closure will allow for the reconstruction and widening of Milan-Oakville Road. The closure is expected to last into late-October 2009.
During the closure period, two signed detour
routes will be in place. The
automobile detour route
(cars, pickups, motorcycles, etc.) will follow
Whittaker Road, Willow Road and Carpenter Road. The
truck detour route will follow Wanty Road, Darling
Road and Plank Road.
Access for local traffic, for those motorists
traveling to residential and business addresses
within the construction work zone, will be
maintained. However, through traffic on
Milan-Oakville Road will be prohibited.
The proposed roadway improvements vary in nature
within the project limits. These improvements
include segments of storm sewer construction,
concrete curb and gutter, full-depth road
reconstruction, roadway widening, hot mix asphalt
paving and the replacement of a cross-road box
culvert structure.
The Washtenaw County Road Commission thanks you in advance for your patience as we undertake these improvements.
Contact
If you have any questions concerning this project, please phone Aaron Berkholz, Construction Supervisor, at (734) 327-6682, or email berkholza@wcroads.org.