The Washtenaw County Road Commission (WCRC) is responsible for road and bridge construction on public roads located outside city and village limits. Road construction projects are selected based on criteria including: pavement condition, traffic counts, available funding, and road classification (primary or local).

Due to limited road funding, WCRC must balance repair types with our available budget and make the right investment at the right time to preserve the overall road network. To learn more about road funding, visit our FAQ.

What are the common types of road construction projects and what do they cost?

The cost of road repairs depends on a number of variables, including the location, type of construction, the number of lanes, lane width, and the condition of the road. Road work typically cost more in urban areas than rural areas. Keeping a road in “good” condition is less expensive than rebuilding a deteriorated road.

Below are some common types of road construction projects. The costs mentioned in the descriptions below are estimates per lane mile. Please note that projects can cost more or less depending on the cost of materials, schedule, traffic volumes, environmental impacts and other factors. Click here for a flyer showing the life of a road.

Pulverize & Resurface

When a road is in “poor” condition, it may be rebuilt through a process of pulverization and resurfacing. WCRC uses a machine called a pulverizer which is capable of breaking up 6-10 inches of existing asphalt pavement. WCRC then recycles and compacts the pulverized asphalt to create a new road base. After establishing the new road base, crews apply two layers of new asphalt to create a smooth, long-lasting road surface.  A pulverized and resurfaced road will last 10-15+ years and costs approximately $400,000 per mile.

Mill & Resurface

Roads that are in “fair” condition are good candidates for a mill and resurfacing project. During a typical mill and resurfacing project, one layer (1.5–2 inches) of existing asphalt is removed (milled) and the road is resurfaced with a new layer of asphalt. A milled and resurfaced road will last around 5 – 7+ years and costs approximately $200,000 per mile. If the road has deteriorated into “poor” condition, milling one layer of the roadway is usually not enough to improve the ride condition and prevent future deterioration and potholes.

Seal Coat (Chip seal and fog seal)

Seal coat is a relatively low-cost surface treatment that seals and prevents water from seeping into the roadway. Seal coat helps prevent potholes and protects the road surface from the damaging effects of weather, sun, and traffic. A seal coat can help extend the life of a road by 3 – 5 years and costs approximately $23,000- 37,000 per mile. WCRC aims to seal coat roads that have been recently resurfaced in order to extend their lifespans.

Chip seal: A thin film of heated liquid asphalt is sprayed onto the road surface, followed immediately by the placement of small aggregate/stones (“chips”). The chips are then embedded into the liquid asphalt with rollers. Traffic can travel on the road approximately 15 minutes after the chip seal treatment is applied, but it is important that motorists do not exceed 35 mph.

Fog seal: Another thin layer of liquid asphalt that helps to seal in the stones and extends the life of a chip seal. WCRC crews will apply a fog seal within a couple of weeks after a road has been chip sealed, depending on the weather. During fog seal, individual lanes or the entire road will be temporarily closed to keep vehicles from driving on the drying fog seal.

Bridges – Routine Maintenance & Reconstruction

Washtenaw County is home to 126 bridges, many of which were built in the early 1900s. Each year WCRC performs preventative maintenance on bridges with available resources. However, a bridge must be completely replaced if it is deemed structurally unsound during WCRC’s routine inspections.

Bridge replacement projects differ in scope depending on the type, size, traffic volume, and environmental surroundings. A bridge replacement will typically take 3-6 months to construct and can cost anywhere from $500,000 to $3 million depending on the size of the project.

Culverts – Repairs & Replacement

WCRC is also responsible for the maintenance of over 2,500 culverts. Culverts allow water to easily flow underneath a road. Culverts are prefabricated and can be round, oval or box-shaped. They can span between 1 to 20 feet. Similar to the Washtenaw County’s bridges, many culverts were built in the early 1900s, have exceeded their lifespans and require repairs or replacements.

Why is this road being treated when our road looks much worse?

Due to limited road funding, WCRC is focused on making the right investment at the right time (asset management) to save taxpayer dollars and extend the service life of our roads.

Asset management is similar to vehicle maintenance. You can wait until the engine fails before you take your car in for repairs, or you can take your car in for routine oil changes. Routine maintenance will make your car run smoother and avoid costly engine repairs. Road work is similar.

WCRC performs preventative maintenance on roads that are already in “good” condition to extend the road’s lifespan and avoid costly reconstruction projects when a road falls into “poor” condition.

Click here to learn more in WCRC’s latest Transportation Asset Management Plan.

Why are you putting “tar and gravel” on our paved road?

The tar and gravel you see on a road is called a chip seal or seal coat. During a chip seal project, a dump truck full of stone locks on to a chip spreader that is pulled backward. A thin layer of liquid asphalt is sprayed down in front of the chip spreader.

During the chip seal process- from the time the gravel is placed on the road to when the excess is swept away- the speed limit is 35 mph.

Chip sealing is a relatively low-cost surface treatment that prevents water from seeping into the roadways, which helps prevent potholes and protects the road surface from the damaging effects of weather, sun, and traffic. A chip seal can help extend the life of a road by 3-5 years.

But for a few exceptions, WCRC fog seal roads after they have been chip sealed. A fog seal is another thin layer of liquid asphalt that is applied once the excess chips have been swept up. This additional treatment helps to seal in the stones and extend the life of a chip seal. WCRC crews will return to fog seal within a couple of weeks after a road has been chip sealed, depending on the weather. Once the fog seal has been applied the road will be temporarily closed, vehicles will be prohibited from driving on it for a couple of hours as it cures.

Will I be able to access my driveway when crews are paving?

Yes, with one exception – when crews are paving directly in front of a driveway, which typically takes 30-60 minutes. During paving operations, traffic must be restricted due to the extremely hot temperature of the asphalt and to minimize damage to the new road surface.

Paving is a moving operation and weather-dependent. There is no exact schedule of when crews will be pave in front of a driveway. If you see crews nearing your residence, let them know your needs and they will assist you in entering or exiting your driveway safely.

What do I do if construction activities, vehicles or materials damage my car?

If your vehicle sustained damage while driving through a construction zone on a road under the jurisdiction of WCRC, you can file a damage claim.

NOTE: The majority of road defect claims are denied under governmental immunity laws.

Please visit our Damage Claim page for more information and the claim packet.

How can I stay informed of upcoming road construction?

During the construction season, there are many ways to stay informed about upcoming work:

  1. Weekly Road Work Schedule – WCRC publishes a weekly road construction schedule for roadwork occurring the following week. Click here to view the latest schedule. 
  2. Road Advisories – WCRC posts road advisories warning of upcoming road closures, lane restrictions, etc. Click here to view the latest advisories.
  3. Project Pages – each construction season, WCRC creates a project web page for major projects occurring throughout the county. Click here to see the Current Project Map. Click on the project name to learn more about each project. The largest projects also include regular project updates throughout construction.

You can subscribe to receive any or all of these communications via email as well. Click here to subscribe.

Why does WCRC remove healthy trees from the roadside?

Trees are an important part of our roadways but they can cause safety and damage concerns when located too close to the road. There are times where WCRC will remove healthy trees from the public road right-of-way before the start of road construction to make room for the work. Trees may also be removed during a roadside safety improvement project.

Click here for WCRC’s Tree Policy.